Home / Guides / The redevelopment

Dharavi redevelopment

After twenty years of plans, the rebuilding of Dharavi has started. Here is who is doing it, who gets a home, what is being torn down and what it means if you visit.

High-rise towers under construction with cranes, beside the low rooftops of Dharavi
Rehab towers are rising first; homes are cleared sector by sector after that.

Booking choice: The Reality Tours walk, from $20 per person. Check dates Tour details

The Dharavi Redevelopment Project aims to replace the slum's homes and workshops with towers, new streets and saleable property, over a timeline officials put at 17 years. A company 80% owned by the Adani Group is building it with the Maharashtra government.

This guide is based on official statements and news reports up to October 2026. Dates move, so we give each one with its source. For the latest news, see our October 2026 update.

The quick answer

The project is run by Adani Navbharat Developers, 80% Adani Group and 20% Maharashtra government, with the state's Dharavi Redevelopment Project authority. The land stays with the city, state and central governments, ministers say. Clearing began in 2026 in Sector 6, and the first 10 rehab towers at Matunga are due from 2029 to 2030. Pre-2000 residents get a free 350 sq ft flat in Dharavi; later arrivals are rehoused outside it. Tours run as normal.

A cleared plot with rubble beside old houses, a hoarding and cranes behind
Clearing has started in Sector 6, on railway land.

What is the Dharavi Redevelopment Project?

A state plan to rebuild Dharavi as a planned township, handed in 2023 to a joint company that is 80% Adani Group and 20% Government of Maharashtra.

The plan dates from a government resolution of 4 February 2004. An earlier tender, won by SecLink in 2019, was cancelled. In the re-tender, Adani Properties bid Rs 5,069 crore in November 2022 and was awarded the contract in July 2023. The special purpose vehicle has changed its name twice: Dharavi Redevelopment Project Pvt Ltd, then Navbharat Mega Developers in December 2024, and now Adani Navbharat Developers (Adani, Oct 2026).

The state body is the DRP, under the Slum Rehabilitation Authority. Officials say about 1 million residents will be rehoused in 1.25 to 1.5 lakh new homes, with 95 million sq ft of rehab housing to be built before 130 million sq ft of saleable space.

Dharavi rooftops at dusk with the towers of Bandra Kurla Complex behind
The land's value comes from its neighbour: the Bandra Kurla Complex.

Who owns Dharavi?

The government, mostly. About half the land belongs to the city corporation (BMC), and the rest to the state and central governments, including Indian Railways.

Housing minister Ashish Shelar told the state assembly in March 2025 that about 50% of the land is owned by the BMC and the rest by the state and central governments, and that "not an inch" had been given to Adani: the land vests with the DRP (PTI via The Week). Those are a minister's words; critics argue the developer gains the value through building rights instead.

Railway land is part of it: the first rehab towers sit on a 22-acre railway plot at Matunga, and railway staff get the first flats there. Kumbharwada's potters hold their land on an old lease, said by one magazine to end in 2032.

Visit with the operator that has explained Dharavi's issues to guests since 2005.

Check dates for the Reality Tours walk

Will Dharavi be demolished?

In stages, yes. The plan is to build rehab towers first and then clear and rebuild Dharavi sector by sector over about 17 years. Demolition has begun in Sector 6.

By 6 August 2026, in Sector 6 (Meghwadi and Ganesh Nagar, about 3,500 homes on railway land), 890 tenements had been vacated and 379 structures demolished, with a 36-storey rehab building under construction (Free Press Journal). Sectors 6 and 1 go first.

Most of Dharavi will look as it does now for years. The workshops, Kumbharwada and the residential lanes that tours visit are still in use in October 2026.

A narrow lane with a painted doorway and rangoli
Most lanes are untouched for now. Sector 6 is the first to go.

What is the redevelopment timeline?

Planned since 2004, awarded in 2023, surveyed in 2025, and building since 2026. The first rehab flats are due in March 2029.

Key dates from official releases and news reports:

DateWhat happened
4 Feb 2004Government resolution approves the township plan
Nov 2022 / Jul 2023Adani wins the re-tender and is awarded the contract
Dec 2024Bombay High Court dismisses SecLink's challenge
7 Mar 2025Supreme Court refuses to stay the project; the case is still pending
Feb to Apr 2025Door-to-door survey passes 67,000 households
28 May 2025Master plan approved
2 Jul 2025First eligibility list, Sector 6
23 Feb 2026118 acres at Malvani, Malad, handed over for ineligible residents
6 Aug 2026890 tenements vacated, 379 structures demolished in Sector 6
2 Oct 2026Dharavi Experience Centre opens, with sample homes
12 Oct 2026Groundbreaking at the Matunga railway site
Mar 2029 to Aug 2030Planned handover of the 10 Matunga towers

Sources: SRA, The Tribune, Free Press Journal and Adani.

Who gets a new home, and where?

Residents of homes from before 1 January 2000 get a free 350 sq ft flat inside Dharavi. Those from 2000 to 2011 can buy a 300 sq ft home, mostly outside. Later arrivals go to rental housing.

  • Before 1 Jan 2000: free 350 sq ft flat in Dharavi, with two toilets, if found eligible.
  • 1 Jan 2000 to 1 Jan 2011: a 300 sq ft home for Rs 2.5 lakh, outside Dharavi according to Business Standard and The Tribune (one 2026 report says inside; it is disputed).
  • Upper-floor tenements: 300 sq ft under a hire-purchase scheme, on rent for 12 years.
  • 2011 to 15 Nov 2022, and others ineligible: rental or hire-purchase housing outside Dharavi, on land such as the 118 acres at Malvani in Malad.

In the first eligibility list, for Sector 6, 229 of 505 tenements were found eligible: 76.6% of the 299 assessed, about 45% of the total (The Tribune). The gap between those numbers is at the heart of the protests.

A cleared plot with rubble beside old houses and cranes behind
Eligibility is decided home by home, and many fall outside the cut-offs.
Dharavi Slum Tour with a Local Guide

Hear how the redevelopment looks from the lanes, with a local guide; the listing offers short and long options.

★ 4.9 · 2 to 7 hours · from $5

Explore the local-guide walk Tour details

What are the Matunga rehab towers?

The first ten rehab buildings, 37 to 39 floors each, on a 22-acre railway plot at Matunga, with 10,432 flats of 350 sq ft and 1,379 shops and workshops.

Ground was broken on 12 October 2026. Adani's release gives the handover schedule as five towers by March 2029, two by August 2029 and three by August 2030. Railway staff get the first allotments. The designers named include Sasaki, Buro Happold and Hafeez Contractor.

Ten days earlier, the chief minister opened the 22,500 sq ft Dharavi Experience Centre with sample flats. The chief minister said in July 2026 that 10,000 rehab homes would be ready in about 18 months; the official schedule above is later.

Walk past the potters and the recycling units, still at work while the towers go up.

Check dates for Dharavi and Dhobi Ghat

Who opposes the Dharavi redevelopment?

Opposition parties, many residents and some businesses. The main fears are eligibility, rehousing outside Dharavi and losing workshops that need ground-floor space.

Shiv Sena (UBT) and Congress oppose the project as handed to Adani; Congress protested in June 2025 over the transfer of the Mother Dairy plot in Kurla. SecLink's case against the tender is still pending in the Supreme Court, which refused to stop the work in 2025 and ordered payments through a single bank account.

For residents, the question is practical. A family whose business is on the ground floor, or who arrived after 2000, may lose either the workshop or the right to stay in Dharavi. Potters in Kumbharwada need kilns, not flats. The film Kaala (2018), about a land grab in Dharavi, shows how political the issue is.

A kiln with stacked clay pots and smoke at dusk
Kilns and workshops do not fit easily into towers. That is the potters' worry.

What does the redevelopment mean for visitors?

Little for now: tours run as before. Over the next decade, the walks will change as sectors are rebuilt.

Guides talk about the project openly, and it is worth asking yours what neighbours think. Do not visit to see Dharavi "before it disappears". It will be a working neighbourhood for years, and that framing is the kind of voyeurism residents dislike.

Expect construction around the Matunga railway land and in Sector 6, which you may see from the train. For context before you go, read the Dharavi facts and the ethics guide.

Dharavi Walking Tour with Reality Tours

A guide who explains the redevelopment from both sides, in a group of six, with cameras left behind.

★ 4.9 · 2.5 to 3.5 hours · from $20

Explore the Reality Tours walk Tour details

Frequently asked questions

Is Adani buying Dharavi?

No, according to the state government: the land stays with public bodies and vests with the DRP. The Adani-led company builds and earns from saleable space and development rights.

When will Dharavi redevelopment be completed?

Officials give an overall timeline of about 17 years. The first rehab towers at Matunga are due between March 2029 and August 2030.

Can you still visit Dharavi during the redevelopment?

Yes. Walking tours run as normal in October 2026. Ask your guide which areas are being cleared.

What happens to Dharavi's businesses?

The master plan includes commercial and industrial units, 1,379 of them in the Matunga towers, but many owners doubt that small workshops will fit.

Ready to book

Choose your walk

Free cancellation up to 24 hours before on every option. Prices are from-prices in USD and move with the season.

Dharavi Walking Tour with Reality Tours

Dharavi Walking Tour with Reality Tours

★ 4.9 · 2.5 to 3.5 hours

  • English-speaking local guide, group of up to six
  • Recycling, pottery, leather and the residential lanes
  • Water or a cold drink at the end
From$20per personCheck dates
Dharavi Slum Tour with a Local Guide

Dharavi Slum Tour with a Local Guide

★ 4.9 · 2 to 7 hours

  • Local guide on foot through Dharavi
  • Workshops, markets and residential lanes
  • Private option on some dates
From$5per personCheck dates
Dharavi & Dhobi Ghat with a Resident Guide

Dharavi & Dhobi Ghat with a Resident Guide

★ 5.0 · 3 hours

  • English-speaking guide who lives in Dharavi
  • Shared or private option
  • Water, food and drinks listed as included
From$3per personCheck dates

Plan your date before you go

Small groups of six, a strict no-camera rule and 80% of post-tax profits to a Dharavi NGO. Free cancellation up to 24 hours before.

Check dates for the Reality Tours walk